The project has been going relatively well,although there have been some problems with resource availability and the project scope has changed more than was expected.The project is now completing one of its phase.Of all decisions the sponsor must consider during an end-of–phase review meeting,the MOST difficult is:()

A.Authorizing scope change for the next phase.
B.Authorizing budget increase for the next phase based on scope changes.
C.Cancelling the project.
D.Decreasing scope to maintain the budget.

题目列表

你可能感兴趣的试题

  • 单项选择题

    You have just finished most of the work on a new system integration project when the seller comes to you with detailed procedures for close out of the contract.The contract included closeout procedures.What should the project manager do?()

    A.Revise the closeout procedures after getting management’s approval.
    B.Get a change order.
    C.Create new procedures that are more complet
    D.Assess the quality of the seller’s new detailed procedures and if they are better than the current procedures.use them.

  • 单项选择题

    During the project,a team member tells you that a major risk identified by the team has occurred.However,it is not as serious as previously thought.What is the FIRST thing you should do?()

    A.Increase the quality standard.
    B.Present this finding to the project team and ask them to verify the team member’s finding.
    C.Investigate changing the contingency plan
    D.Notify management.