单项选择题X 纠错

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.

A.activity
B.work
C.currency
D.time

参考答案:
查答案就用赞题库小程序 还有拍照搜题 语音搜题 快来试试吧
无需下载 立即使用

你可能喜欢

单项选择题

A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources

单项选择题

A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project

单项选择题

A.physical
B.network
C.transport
D.application

赞题库

赞题库-搜题找答案

(已有500万+用户使用)


  • 历年真题

  • 章节练习

  • 每日一练

  • 高频考题

  • 错题收藏

  • 在线模考

  • 提分密卷

  • 模拟试题

无需下载 立即使用

版权所有©考试资料网(ppkao.com)All Rights Reserved