(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
A.F-S
B.F-F
C.S-F
D.S-S
你可能喜欢
单项选择题
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources
单项选择题
A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project
单项选择题
A.bridge
B.server
C.router
D.switch
单项选择题
A.users
B.servers
C.producers
D.suppliers
单项选择题
A.share
B.Mitigate
C.Transfer
D.Acceptance
单项选择题
A.program
B.portfolio
C.projectoflargesize
D.PMO
单项选择题
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung