单项选择题X 纠错
A.r(i,j)=tL(j)-[tL(i) +t(i,j)]
B.r(i,j)=tL(j)-[tE(i) +t(i,j)]
C.r(i,j)=tE(j)-[tL(i) +t(i,j)]
D.r(i,j)=tE(j)-[tE(i) +t(i,j)]
你可能喜欢
单项选择题
A.R(1,2)=0,R(2,4)=0,R(4,6)=0
B.R(1,2)=0,R(3,5)=0,R(5,6)=0
C.R(1,2)=0,R(2,3)=0,R(3,5)=0,R(5,6)=0
D.R(1,2)=0,R(2,3)=0,R(3,4)=0,R(4,6)=0
单项选择题
A.工程的总工期不变,关键路线减少
B.工程的总工期不变,关键路线不变
C.工程的总工期缩短,关键路线减少
D.工程的总工期缩短,关键路线不变
单项选择题
A.工序单时差r(i,j)=0,工序总时差R(i,j)=0
B.工序单时差r(i,j)>0,工序总时差R(i,j)=0
C.工序单时差r(i,j)=0,工序总时差R(i,j)>0
D.工序单时差r(i,j)>0,则工序总时差R(i,j)>0