单项选择题

某工程包括A、B、C、D、E、F、G七个作业,各个作业的紧前作业、所需时间、所需人数如表12-10所示:该工程的计算工期为(1)周。按此工期,整个工程至少需要(2)人。

单项选择题某流水线浮点加法器分为五级,若每一级所需要的时间分别是6ns、7ns、8ns、9ns和6ns,则此流水线的最大加速比为(1)。若每一级的时间均为7ns,则最大加速比为(2)。

问答题

参考答案:

1)物理层
2)数据链路层
3)网络层
4)传输层
5)会话层
6)表示层
7)应用层

单项选择题

SOX is an alternative(1)for XML.It is useful for reading and creating XML content in a(2).editor.It is then easily transformed into proper XML.SOX was created because developers can spend a great deal oftime with raw XML.For many ofus,thepopular XML(3)have not reached a point where their tree views,tables and forms can completely substitute for the underlying(4)languagE.This is not surprising when one considers that developers still use a text view,albeit enhanced,for editing other languages such as Java)SOX uses(5)to represent the structure of an XML document,which eliminates the need for closing tags and a number of quoting devices.The result is surprisingly clear.

赞题库

赞题库-搜题找答案

(已有500万+用户使用)


  • 历年真题

  • 章节练习

  • 每日一练

  • 高频考题

  • 错题收藏

  • 在线模考

  • 提分密卷

  • 模拟试题

无需下载 立即使用

版权所有©考试资料网(ppkao.com)All Rights Reserved