问答题
You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:
A.The project is operating at a favorable cost efficiency ratio.
B.the project is spending more than planned
C.the project is behind schedule
D.the project is ahead of schedule
E.B and C