You have to finish a project with in 2 weeks and your lead developer had to take 1 week leave due to personal emergency.Another project manager has agreed to loan the service of his lead developer for 1 week.You are taking his help and completing the project.This case is an example of () (Choose the best answer).

A.fast tracking
B.crashing
C.risk management
D.resource leveling